Building of NFSA nearing completion

Construction work of the NFSA building started in March 2014 is underway full swing. The Capital Development Authority (CDA) has informed that the civil work of Admin block / Lab block and Training block will be completed by the end of November, 2015. Tendering process of walk ways and landscaping has already been successfully done by the CDA and the physical work has also started for that. The building will be handed over to NFSA in start of December 2015 and the NFSA office (which is currently being housed in a rented building) will be shifted to its own premises.

Project Director NFSA examining the construction work